The next stage in improving facilities for pupils at Portfield School will be decided by Pembrokeshire County Council Cabinet’s first meeting of 2023.

The submission of the Outline Business Case (OBC) for plans to improve the condition of school buildings and increase capacity at the school for children and young people with complex needs is recommended for approval by senior Councillors on Monday, January 9.

The OBC for Portfield School situated in Haverfordwest was considered by the Sustainable Communities for Learning Strategic Programme Board in December and the current estimated cost of the project is £30,307,000 including cost of achieving Net Zero Carbon.

Pembrokeshire County Council’s contribution towards the project is £6,651,293 as a result of a 75 per cent Welsh Government intervention rate on all special school related projects.

Cabinet will note that a reduction in the overall 21st Century School Band B Programme capital envelope results in a £3million funding shortfall that will potentially be mitigated by design efficiencies, value engineering, reinstated Welsh Government funding or prudential borrowing.

Cabinet will meet at 10 am and the meeting will be webcast.